GENERAL
PROJECT INFORMATION |
|
Project Title: |
Time Warner
Cable Malibu Hills Fiber Optic Line Installation |
|
Location: |
Malibu Hills
Rd and Calabasas Hills Rd |
|
Construction Dates: |
November 16,
2009 - December 25, 2009 |
|
Contact: |
Pierce
Communications Services - Ronald Pierce: 714-720-0568 |
The scope of this project is the installation of approximately 4,500
ft of under ground conduit and fiber optic cable incorporating HDD
(Horizontal Directional Drilling) method and the installation of
pull boxes and hand holes in the sidewalk and parkways. This project
is an expansion of service capability for Time Warner Cable. The new
cable will provide service to the Archstone Apartments complex on
Meadow Creek between Lost Hills Rd and Las Virgenes Rd. The limits
of construction of the work is Malibu Hills west from Lost Hills Rd
to Calabasas Hills, then south on Calabasas Hills to Lost Hills Rd. |
|